Project Milestone Status

Project Milestones Status

Project Milestone As per Concession Agreement Actual Delay (No. of months) Current Status
Days
from
Appointed Date
Physical Progress (%) Scheduled Date Physical Progress (%) Achieved Date
Project Milestone-I 180 20.00% 15th Oct 2024 20% 24th Feb 2025 132 days 43.067%
Project Milestone-II 360 35.00% 13th Apr 2025 35% 20th June 2025 68 days
Project Milestone-III 550 75.00% 20th Oct 2025      
Schedule Completion 730 100.00% 18th Apr 2026