| Project Milestone | As per Concession Agreement | Actual | Delay (No. of months) | Current Status | |||
|---|---|---|---|---|---|---|---|
| Days from Appointed Date |
Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | |||
| Project Milestone-I | 180 | 20.00% | 15th Oct 2024 | 20% | 24th Feb 2025 | 132 days | 43.067% |
| Project Milestone-II | 360 | 35.00% | 13th Apr 2025 | 35% | 20th June 2025 | 68 days | |
| Project Milestone-III | 550 | 75.00% | 20th Oct 2025 | ||||
| Schedule Completion | 730 | 100.00% | 18th Apr 2026 | ||||